Construction continues at historic USA Softball Hall of Fame Complex where changes to the main stadium are happening everyday, seven days a week. THE PAST WEEK » With the first coat of paint in the basement completed, the ceiling grid has also started with tile nearing completion in the bathrooms. Press box exterior framing is complete, while green sheathing installation continues. Laying concrete masonry unit (CMU), also known as the concrete blocks, at the second floor is underway and at the bearing on the third-base side. Fire suppression crews continue working and have moved from the basement to concourse level. Weather barrier is also being installed at joints, screws, penetrations and steel abutment. Photos show you front-entrance views of the Northwest (third base) and Northeast (first base) sides, as well as the media hospitality room and press conference room.
|